![Church of Christ School-page-001](https://www.action4schools.gi/wp-content/uploads/2014/01/Church-of-Christ-School-page-001-1230x1592.jpg)
![July 2011 - Top view of the school before refurbishment](https://www.action4schools.gi/wp-content/uploads/2014/01/Back-left-hand-side-view--1230x923.jpg)
July 2011 - Top view of the school before refurbishment
![Church of Christ July 2011](https://www.action4schools.gi/wp-content/uploads/2014/01/043-1230x923.jpg)
July 2011 - Interior of school
![Inner view-1](https://www.action4schools.gi/wp-content/uploads/2014/01/Inner-view-11-1230x923.jpg)
Inside of the school as it was up to August 2011
![Picture 061](https://www.action4schools.gi/wp-content/uploads/2014/01/Picture-061-1230x923.jpg)
Classroom
![Front view-2](https://www.action4schools.gi/wp-content/uploads/2014/01/Front-view-21-1230x923.jpg)
School building before refurbishment
![Back view](https://www.action4schools.gi/wp-content/uploads/2014/01/Back-view-1230x923.jpg)
School building before refurbishment
![Desc](https://www.action4schools.gi/wp-content/uploads/2014/01/Church-of-Christ-Sept.-2012-11.jpg)
Latrines before refurbishment
![041](https://www.action4schools.gi/wp-content/uploads/2014/01/041-1230x923.jpg)
July 2011 - Latrines and school in background
![Picture 060](https://www.action4schools.gi/wp-content/uploads/2014/01/Picture-060-1230x923.jpg)
The school roof was a tarpaulin
![Top view-3](https://www.action4schools.gi/wp-content/uploads/2014/01/Top-view-3-1230x923.jpg)
School before refurbishment
![Picture 062](https://www.action4schools.gi/wp-content/uploads/2014/01/Picture-062-1230x923.jpg)
![Off loading of materials for christ church pri. sch Rengent](https://www.action4schools.gi/wp-content/uploads/2014/01/Off-loading-of-materials-for-christ-church-pri.-sch-Rengent-1230x923.jpg)
August 2013 - Works begin
![004](https://www.action4schools.gi/wp-content/uploads/2014/01/004-1230x923.jpg)
August 2013 - Work underway
![September 2011 - Construction underway](https://www.action4schools.gi/wp-content/uploads/2014/01/Construction2-1230x923.jpg)
August 2011 - Construction underway
![Partitioning to three class room](https://www.action4schools.gi/wp-content/uploads/2014/01/Partitioning-to-three-class-room-1230x923.jpg)
August 2011 - Works underway
![Construction1](https://www.action4schools.gi/wp-content/uploads/2014/01/Construction1-1230x923.jpg)
August 2011 - Construction underway
![DSCF1301](https://www.action4schools.gi/wp-content/uploads/2014/01/DSCF1301-1230x923.jpg)
August 2013 - Work underway
![001](https://www.action4schools.gi/wp-content/uploads/2014/01/001-1230x923.jpg)
Augsut 2011 - Works underway
![DSCF1289](https://www.action4schools.gi/wp-content/uploads/2014/01/DSCF1289-1230x923.jpg)
August 2013 - Work underway
![August 2011](https://www.action4schools.gi/wp-content/uploads/2014/01/DSCF1290-1230x923.jpg)
August 2011 - Construction under way
![Finished school](https://www.action4schools.gi/wp-content/uploads/2014/01/Finished-school-1230x923.jpg)
September 2011 - School nearly ready
![Church of Christ Sept 2011](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0069-1230x923.jpg)
September 2011 - The school was blessed and officially opened
![Latrines 2](https://www.action4schools.gi/wp-content/uploads/2014/01/Latrines-2-1230x823.jpg)
June 2012 - New latrines built
![Church of Christ Sept. 2012 (2)](https://www.action4schools.gi/wp-content/uploads/2014/01/Church-of-Christ-Sept.-2012-2.jpg)
September 2012
![Gib Flag](https://www.action4schools.gi/wp-content/uploads/2014/01/Gib-Flag-1230x923.jpg)
September 2011 - Gibraltar Flag at the school opening
![New generator donated by AKIN Geberltar to Church of Christ sch. Regent](https://www.action4schools.gi/wp-content/uploads/2014/01/New-generator-donated-by-AKIN-Geberltar-to-Church-of-Christ-sch.-Regent.jpg)
Power generator provided May 2013
![IMG_0232](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0232-1230x923.jpg)
June 2013 - Night classes possible
![IMG_0198](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0198-1230x923.jpg)
May 2013 - Local carpenter making new furniture
![IMG_0154](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0154-1230x923.jpg)
May 2013 - New furniture
![IMG_0196](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0196-1230x923.jpg)
May 2103 - Great to see so many new items ready for use
![Teacher new table , chair , wall cabinet & electrical aplinces on wall](https://www.action4schools.gi/wp-content/uploads/2014/01/Teacher-new-table-chair-wall-cabinet-electrical-aplinces-on-wall.jpg)
May 2013 - New cabinet provided
![New deskes in use](https://www.action4schools.gi/wp-content/uploads/2014/01/New-deskes-in-use.jpg)
May 2013 - New chairs and desks being put to good use
![IMG_1165](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1165-1230x923.jpg)
May 2013 - New chairs and desks provided
![IMG_1164](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1164-1230x923.jpg)
May 2013 - Church of Christ has come a long way in 2 years thanks to yoru support. Thank you!
![IMG_0131](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_01311-1230x923.jpg)
May 2013 - Builders getting ready to build the water tank tower
![IMG_0140](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_01401-1230x923.jpg)
![IMG_0112](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_01121-1230x923.jpg)
May 2103 - Building blocks for the water tank tower
![IMG_0205](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0205-1230x923.jpg)
May 2013 - The water tower is nearly ready
![Test](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0332-1230x923.jpg)
May 2013 - 1000 litre water tank provided
![IMG_1155](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1155-1230x923.jpg)
May 2013 - 1000 litre water tank provided and nearly ready to be used
![Hand washing after toilet by head teacher](https://www.action4schools.gi/wp-content/uploads/2014/01/Hand-washing-after-toilet-by-head-teacher.jpg)
May 2013 - Hand washing facilities
![IMG_1150](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1150-1230x923.jpg)
May 2013 - Water will improve hygiene
![Latrines & Sink](https://www.action4schools.gi/wp-content/uploads/2014/01/Latrines-Sink.jpg)
May 2013 - Water was provided for the latrines
![IMG_0266](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0266-1230x923.jpg)
May 2013 - One of the new sinks provided
![market vendor makeing use of the sink](https://www.action4schools.gi/wp-content/uploads/2014/01/market-vendor-makeing-use-of-the-sink.jpg)
May 2013 - Sinks provided, useful for washing utensils, etcetera
![IMG_0331](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0331-1230x923.jpg)
May 2013 - Finally!! Water in the school!!
![Tap for drinking](https://www.action4schools.gi/wp-content/uploads/2014/01/Tap-for-drinking-.jpg)
May 2103 - Water is life!
![IMG_0329](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0329-1230x923.jpg)
May 2103 - Children will not have to travel far again for water
![IMG_0048](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0048-1230x923.jpg)
Volleyball is popular!
![IMG_0049](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0049-1230x923.jpg)
Keen to play volleyball
![Chairs,Larning materials,Foot ball valley ball & set of vests](https://www.action4schools.gi/wp-content/uploads/2014/01/ChairsLarning-materialsFoot-ball-valley-ball-set-of-vests-1230x923.jpg)
May 2013 - Sports equipment was provided
![IMG_0039](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0039-1230x923.jpg)
May 2013 - Football kits were provided
![IMG_0047](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0047-1230x923.jpg)
May 2013 - Sports equipment provided
![IMG_0040](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_0040-1230x923.jpg)
May 2013 - Football kits provided
![IMG_1168](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1168-1230x923.jpg)
A school extension is required, there are too many children per classroom
![IMG_1167](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1167-1230x923.jpg)
Too many children for the space available
![IMG_1169](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1169-1230x923.jpg)
More space is required
![IMG_1183](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1183-1230x923.jpg)
May 2013 - This way for the new Church of Christ Primary School
![IMG_1181](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_1181-1230x923.jpg)
New school, new future ahead.... thank you for your support !! These children deserve a better environment, thank you for your support! PLEASE CONSIDER SETTING UP A MONTHLY STANDING ORDER TO SUPPORT THEM IN THEIR EDUCATION - YOU WILL MAKE A DIFFERENCE 100% GUARANTEED. Please contact info@action4schools.gi
![IMG_3130](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_3130.jpg)
March 2014 - We replaced the holes with windows. This drastically improved ventilation and offered much needed natural light in the classrooms.
![Dimolishing of window balusters](https://www.action4schools.gi/wp-content/uploads/2014/01/Dimolishing-of-window-balusters-.jpg)
March 2014 - We replaced the holes with windows. This drastically improved ventilation and offered much needed natural light in the classrooms.
![IMG_3105](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_3105.jpg)
March 2014 - We replaced the holes with windows. This drastically improved ventilation and offered much needed natural light in the classrooms.
![Fixing of window guide & internal shurters](https://www.action4schools.gi/wp-content/uploads/2014/01/Fixing-of-window-guide-internal-shurters.jpg)
March 2014 - Bars were fitted for additional security.
![IMG_3115](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_3115.jpg)
March 2014 - We replaced the holes with windows. This drastically improved ventilation and offered much needed natural light in the classrooms.
![IMG_3123](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_3123.jpg)
March 2014 - We replaced the holes with windows. This drastically improved ventilation and offered much needed natural light in the classrooms.
![IMG_3122](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_3122.jpg)
March 2014 - We replaced the holes with windows. This drastically improved ventilation and offered much needed natural light in the classrooms.
![IMG_3125](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_3125.jpg)
March 2014 - We replaced the holes with windows. This drastically improved ventilation and offered much needed natural light in the classrooms.
![IMG_3129](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG_3129.jpg)
March 2014 - Bars were fitted for additional security.
![SAM_5555 - Copy](https://www.action4schools.gi/wp-content/uploads/2014/01/SAM_5555-Copy.jpg)
May 2014 - The school was painted
![SAM_5556 - Copy](https://www.action4schools.gi/wp-content/uploads/2014/01/SAM_5556-Copy.jpg)
May 2014 - Great to see improved conditions.
![SAM_5579](https://www.action4schools.gi/wp-content/uploads/2014/01/SAM_5579.jpg)
May 2014 - Windows make a big difference to pupils
![SAM_5560](https://www.action4schools.gi/wp-content/uploads/2014/01/SAM_5560.jpg)
May 2014 - Better ventilation and improved natural light provided by the new windows.
![SAM_5562](https://www.action4schools.gi/wp-content/uploads/2014/01/SAM_5562.jpg)
May 2014 - Break time!
![SAM_5564](https://www.action4schools.gi/wp-content/uploads/2014/01/SAM_5564.jpg)
May 2014 - Side view with the water tank in the background
![SAM_5570](https://www.action4schools.gi/wp-content/uploads/2014/01/SAM_5570.jpg)
May 2014 - New windows and building freshly painted.
![SAM_5559](https://www.action4schools.gi/wp-content/uploads/2014/01/SAM_5559.jpg)
May 2014 - Church of Christ has come a long way since 20111, thank you for your support!!
![IMG-20170411-WA0009](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG-20170411-WA0009.jpg)
April 2017 - The roof was leaking and it was replaced and we fitted a new ceiling
![IMG-20170411-WA0006](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG-20170411-WA0006.jpg)
April 2017 - The roof was leaking and it was replaced and we fitted a new ceiling
![IMG-20170411-WA0007](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG-20170411-WA0007.jpg)
April 2017 - The roof was leaking and it was replaced and we fitted a new ceiling
![IMG-20170411-WA0017](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG-20170411-WA0017.jpg)
April 2017 - The roof was leaking and it was replaced and we fitted a new ceiling
![IMG-20170411-WA0015](https://www.action4schools.gi/wp-content/uploads/2014/01/IMG-20170411-WA0015.jpg)
April 2017 - The roof was leaking and it was replaced and we fitted a new ceiling